Cost and time overrun in construction projects in a multicultural setting

Ågren, Robert LU orcid ; Jingmond, Monika LU and Landin, Anne LU (2011) Second Conference on Advances in Engineering and Technology p.291-297
Abstract
Delays and cost overruns are frequent problems in the construction industries of both developed and developing countries. Studies aimed at identifying the causes are often undertaken with just a broad appreciation of the construction process and frequently do not deal with multicultural issues when considering the reasons for overruns. The paper critically reviews existing attempts to uncover the cause of changes in specification that can impact on cost and time, leading to overruns in both. Existing methods are evaluated from a multicultural perspective and are found to be deficient in a number of respects. The research suggests an alternative way forward in order to advance understanding of a multicultural approach. The proposal is to... (More)
Delays and cost overruns are frequent problems in the construction industries of both developed and developing countries. Studies aimed at identifying the causes are often undertaken with just a broad appreciation of the construction process and frequently do not deal with multicultural issues when considering the reasons for overruns. The paper critically reviews existing attempts to uncover the cause of changes in specification that can impact on cost and time, leading to overruns in both. Existing methods are evaluated from a multicultural perspective and are found to be deficient in a number of respects. The research suggests an alternative way forward in order to advance understanding of a multicultural approach. The proposal is to adopt cognitive mapping in order to establish a common theory that would help to describe the different impacts that changes in specification have in industrialized and developing countries. (Less)
Please use this url to cite or link to this publication:
author
; and
organization
publishing date
type
Chapter in Book/Report/Conference proceeding
publication status
published
subject
keywords
cognitive mapping, culture, construction, cost overrun, time overrun
host publication
Proceedings of the Second International Conference on Advances in Engineering and Technology
editor
Mwakali, Jackson and Alinaitwe, Henry
pages
7 pages
publisher
Macmillan
conference name
Second Conference on Advances in Engineering and Technology
conference location
Entebbe, Uganda
conference dates
2011-01-31 - 2011-02-01
ISBN
978-9970-214-00-7
language
English
LU publication?
yes
id
3660f3aa-8601-4066-a80c-13994511cc01 (old id 1785165)
date added to LUP
2016-04-04 10:41:09
date last changed
2018-11-21 21:00:12
@inproceedings{3660f3aa-8601-4066-a80c-13994511cc01,
  abstract     = {{Delays and cost overruns are frequent problems in the construction industries of both developed and developing countries. Studies aimed at identifying the causes are often undertaken with just a broad appreciation of the construction process and frequently do not deal with multicultural issues when considering the reasons for overruns. The paper critically reviews existing attempts to uncover the cause of changes in specification that can impact on cost and time, leading to overruns in both. Existing methods are evaluated from a multicultural perspective and are found to be deficient in a number of respects. The research suggests an alternative way forward in order to advance understanding of a multicultural approach. The proposal is to adopt cognitive mapping in order to establish a common theory that would help to describe the different impacts that changes in specification have in industrialized and developing countries.}},
  author       = {{Ågren, Robert and Jingmond, Monika and Landin, Anne}},
  booktitle    = {{Proceedings of the Second International Conference on Advances in Engineering and Technology}},
  editor       = {{Mwakali, Jackson and Alinaitwe, Henry}},
  isbn         = {{978-9970-214-00-7}},
  keywords     = {{cognitive mapping; culture; construction; cost overrun; time overrun}},
  language     = {{eng}},
  pages        = {{291--297}},
  publisher    = {{Macmillan}},
  title        = {{Cost and time overrun in construction projects in a multicultural setting}},
  year         = {{2011}},
}