Gjutet med god leveransprecision!? - En studie i hur låg leveransprecision från leverantör påverkar produktionen på ITT Flygt AB

Alftén, Andreas ; Andersson, Johan and Toll, Anders (2004) MIO920
Production Management
Abstract
Problem discussion: The internal foundry of ITT Flygt occasionally has problems
with on-time delivery to the product workshops. This could
lead to extra costs regarding labour and stock keeping.
ITT Flygt are today unaware of the extent of these
costs.
Objectives: The main objective of the master thesis is to investigate the
effects of low delivery accuracy from the foundry to PVC. This
main objective is reached by three partial objectives: to
describe and explain the value system for small- and medium
sized pumps, to map and understand the manufacturing
process in the foundry and in PVC, and to in detail map the
machining process of oil house, impellers, and pump housing
in PVC.
Method: In the master thesis a method of... (More)
Problem discussion: The internal foundry of ITT Flygt occasionally has problems
with on-time delivery to the product workshops. This could
lead to extra costs regarding labour and stock keeping.
ITT Flygt are today unaware of the extent of these
costs.
Objectives: The main objective of the master thesis is to investigate the
effects of low delivery accuracy from the foundry to PVC. This
main objective is reached by three partial objectives: to
describe and explain the value system for small- and medium
sized pumps, to map and understand the manufacturing
process in the foundry and in PVC, and to in detail map the
machining process of oil house, impellers, and pump housing
in PVC.
Method: In the master thesis a method of qualitative character is used
but also contains a large amount of data that is treated
quantitatively.
Conclusions: The major costs at PVC caused by the foundry's low delivery
accuracy consists of the extra work that PVC personnel have to
do in order to maintain their own production. Costs emerge
both from early as well as late delivered material. Another
effect of the low delivery accuracy is that it complicates
internal improvement and inventory planning for PVC. The
authors believe that better delivery accuracy would make
essential stock reduction possible. (Less)
Please use this url to cite or link to this publication:
author
Alftén, Andreas ; Andersson, Johan and Toll, Anders
supervisor
organization
course
MIO920
year
type
M1 - University Diploma
subject
keywords
Delivery accuracy, inventory planning, ABC, ITT Flygt, foundry, production management, logistics, process mapping
other publication id
04/5214
language
Swedish
id
2007065
date added to LUP
2011-06-30 11:35:27
date last changed
2011-06-30 11:35:27
@misc{2007065,
  abstract     = {{Problem discussion: The internal foundry of ITT Flygt occasionally has problems
with on-time delivery to the product workshops. This could
lead to extra costs regarding labour and stock keeping.
ITT Flygt are today unaware of the extent of these
costs.
Objectives: The main objective of the master thesis is to investigate the
effects of low delivery accuracy from the foundry to PVC. This
main objective is reached by three partial objectives: to
describe and explain the value system for small- and medium
sized pumps, to map and understand the manufacturing
process in the foundry and in PVC, and to in detail map the
machining process of oil house, impellers, and pump housing
in PVC.
Method: In the master thesis a method of qualitative character is used
but also contains a large amount of data that is treated
quantitatively.
Conclusions: The major costs at PVC caused by the foundry's low delivery
accuracy consists of the extra work that PVC personnel have to
do in order to maintain their own production. Costs emerge
both from early as well as late delivered material. Another
effect of the low delivery accuracy is that it complicates
internal improvement and inventory planning for PVC. The
authors believe that better delivery accuracy would make
essential stock reduction possible.}},
  author       = {{Alftén, Andreas and Andersson, Johan and Toll, Anders}},
  language     = {{swe}},
  note         = {{Student Paper}},
  title        = {{Gjutet med god leveransprecision!? - En studie i hur låg leveransprecision från leverantör påverkar produktionen på ITT Flygt AB}},
  year         = {{2004}},
}