Public Private Partnership - vägen mot en effektiv hållbar utveckling?
(2019) STVA22 20182Department of Political Science
- Abstract
- Our climate is a common responsibility for all countries. The European Investment Bank is playing a big role by regularly providing sub Saharan countries with financial resources so that they can take part of the work for a sustainable environment. Being the world's largest donor entails a great responsibility to act efficiently. This essay aims to investigate how the European Investment Bank uses the financial instrument PPP (Public Private Partnership). The essay aims to focus primarily on the effectiveness of the financial instrument and how it is being used through the African Infrastructure Fund on a project level.
In order to analyzing this matter, a comparative case study will be done focusing on two projects. Lake Turkana Wind... (More) - Our climate is a common responsibility for all countries. The European Investment Bank is playing a big role by regularly providing sub Saharan countries with financial resources so that they can take part of the work for a sustainable environment. Being the world's largest donor entails a great responsibility to act efficiently. This essay aims to investigate how the European Investment Bank uses the financial instrument PPP (Public Private Partnership). The essay aims to focus primarily on the effectiveness of the financial instrument and how it is being used through the African Infrastructure Fund on a project level.
In order to analyzing this matter, a comparative case study will be done focusing on two projects. Lake Turkana Wind Power located in Kenya and Ruzizi III PPP which is a project for hydroelectric in Rwanda, Burundi and Congo. In order to obtain a result the investigation uses the theoretical framework aid conditionality, throughput- and output legitimacy to analyze the effectiveness and the quality of these projects. The result estimates that Ruzizi III is delayed due to disagreements between the three governments and private actors. Also, the work is made even more difficult by the political instability prevailing in these countries. Lake Turkana on the other hand is located in a comparatively more politically stable country where it has been easier to reach consensus since it is only one government and fewer actors involved. Shown from our results it is easier for parties to reach consensus if the state is politically stable and has knowledge about the functioning of the PPP. If the PPP strategy are being applied properly it will improve the effectiveness of the aid and therefore make a contribution to our environment. (Less)
Please use this url to cite or link to this publication:
http://lup.lub.lu.se/student-papers/record/8964808
- author
- Cronquist, Lina LU and Ekman, Beata LU
- supervisor
- organization
- alternative title
- En komparativ fallstudie om AITF:s projekt Lake Turkana Wind Power och Ruzizi III PPP
- course
- STVA22 20182
- year
- 2019
- type
- L2 - 2nd term paper (old degree order)
- subject
- keywords
- Aid conditionality, AITF, Blending instrument, EIB, Output legitimacy, PPP, Throughput legitimacy, Utvecklingsbistånd
- language
- Swedish
- id
- 8964808
- date added to LUP
- 2019-02-22 15:02:44
- date last changed
- 2019-02-22 15:02:44
@misc{8964808, abstract = {{Our climate is a common responsibility for all countries. The European Investment Bank is playing a big role by regularly providing sub Saharan countries with financial resources so that they can take part of the work for a sustainable environment. Being the world's largest donor entails a great responsibility to act efficiently. This essay aims to investigate how the European Investment Bank uses the financial instrument PPP (Public Private Partnership). The essay aims to focus primarily on the effectiveness of the financial instrument and how it is being used through the African Infrastructure Fund on a project level. In order to analyzing this matter, a comparative case study will be done focusing on two projects. Lake Turkana Wind Power located in Kenya and Ruzizi III PPP which is a project for hydroelectric in Rwanda, Burundi and Congo. In order to obtain a result the investigation uses the theoretical framework aid conditionality, throughput- and output legitimacy to analyze the effectiveness and the quality of these projects. The result estimates that Ruzizi III is delayed due to disagreements between the three governments and private actors. Also, the work is made even more difficult by the political instability prevailing in these countries. Lake Turkana on the other hand is located in a comparatively more politically stable country where it has been easier to reach consensus since it is only one government and fewer actors involved. Shown from our results it is easier for parties to reach consensus if the state is politically stable and has knowledge about the functioning of the PPP. If the PPP strategy are being applied properly it will improve the effectiveness of the aid and therefore make a contribution to our environment.}}, author = {{Cronquist, Lina and Ekman, Beata}}, language = {{swe}}, note = {{Student Paper}}, title = {{Public Private Partnership - vägen mot en effektiv hållbar utveckling?}}, year = {{2019}}, }