Funktionsentreprenader inom Järnväg - möjligheter och hinder

Siddique, Samuel (2009)
Civil Engineering - Railway Construction (BSc)
Abstract
The transformation within the swedish infrastructure has been a slow process from the
beginning of time. For almost a decade, the traditional form of contracting regarding
buildings and foremost infrastructure has evolved contracting involving the owner to define
the outcome of the product, regardless involvement from the supposed contractor. As for
the swedish market, the traditional design-bid-build (DBB) have been the primary choice of
contracting. Although changes have been made over time regarding contracting forms
within the road administration, the railway sector has not improved or justified changes
regarding choice of contracting, they have conducted same contracting relationships
between them and the contractor.
This... (More)
The transformation within the swedish infrastructure has been a slow process from the
beginning of time. For almost a decade, the traditional form of contracting regarding
buildings and foremost infrastructure has evolved contracting involving the owner to define
the outcome of the product, regardless involvement from the supposed contractor. As for
the swedish market, the traditional design-bid-build (DBB) have been the primary choice of
contracting. Although changes have been made over time regarding contracting forms
within the road administration, the railway sector has not improved or justified changes
regarding choice of contracting, they have conducted same contracting relationships
between them and the contractor.
This bachelor thesis, conducted at the Swedish railway administration with supervision of
professor Kristian Widén at Lunds University, explores the forces behind the new era of
contracting within the railway administration. This bachelor thesis focuses mainly on
contracting regarding design-build-operate-main (DBOM), the new contracting formula
between the owner and the contractor. Studies within the area of DBOM, shows that there
are some potential regarding this kind of contracting but the railway sector is yet to be more
efficient regarding administration. Furthermore, studies shows that DBOM might be a
possible contract type within some technological areas of the railway sector and some
minor projects as well. The core subject of this thesis is to evaluate the forces behind
implementation of a possible contracting type like DBOM within the railway sector. The
outcome of this studies and conclusion drawn by the author shows that implementation of
the DBOM contracting type, as mentioned before, is yet to be implemented in minor fields
within the railway sector.
Regarding finance and infrastructure developments, the literature studies made within the
area of financing of infrastructure developments, delivers the theory of three kinds of
financing models within the infrastructure: government subsidy, government granted loan
and Public-Private-Partnership. Furthermore, some forces within the swedish government
solemnly issues that Public-Private-Partnership venture is equal DBOM contracting.
Studies regarding procurement shows that there various types of problems regarding the
process of procurement within the swedish railway administration and the infrastructure
area as well, could be shortened and more effective. The analyze regarding procurement
within the swedish railway administration, conducts certain amount of conclusion and
foremost that new kind of procurement method should be implemented within the swedish
railway administration, as of E-procurement or equal.
This thesis also contains a case study, Mälarbanan. The reason why a case study has been
conducted, is to evaluate whether if DBOM contracting type should be implemented within
Mälarbanan, a railway line between Tomteboda and Kallhäll. The analyze intermediates
possible threats regarding DBOM contracting type. Foremost, the DBOM contracting type
should not be implemented whereas there are some tunnels involved in the contract thus the
outcome (product) might differ from the request proposal and the specification given by the
owner, the swedish railway administration i.e. Secondly, the DBOM contracting form
should not be implemented regarding a railway line like Mälarbanan, the length of line
should be taken to consideration. Although there are some major/minor issues regarding
DBOM contracting type, the study recommends the swedish railway administration that
minor contracts should be the primary choice of the case of Mälarbanan.
The conclusion made by the author is regarding the swedish railway administration. The
analyze shows that and the conclusion conducted by the author relates to effectiveness and
the new kind of structure. Recent administration structures lacks efficiency regarding
implementation of new contracting types and as a result of lack of effectiveness have led to
consequences regarding lack of bids and lack of competition between entrepreneurs, but
foremost lack of innovation within the railway sector. Keywords: DBOM, procurement, effectiveness, finance. (Less)
Please use this url to cite or link to this publication:
author
Siddique, Samuel
organization
year
type
M2 - Bachelor Degree
subject
keywords
funktionsentreprenad, entreprenadformer, finansiering, Railway transport technology, Järnvägstransportteknik
language
Swedish
id
1353910
date added to LUP
2009-03-12 00:00:00
date last changed
2018-10-18 09:59:56
@misc{1353910,
  abstract     = {{The transformation within the swedish infrastructure has been a slow process from the
beginning of time. For almost a decade, the traditional form of contracting regarding
buildings and foremost infrastructure has evolved contracting involving the owner to define
the outcome of the product, regardless involvement from the supposed contractor. As for
the swedish market, the traditional design-bid-build (DBB) have been the primary choice of
contracting. Although changes have been made over time regarding contracting forms
within the road administration, the railway sector has not improved or justified changes
regarding choice of contracting, they have conducted same contracting relationships
between them and the contractor.
This bachelor thesis, conducted at the Swedish railway administration with supervision of
professor Kristian Widén at Lunds University, explores the forces behind the new era of
contracting within the railway administration. This bachelor thesis focuses mainly on
contracting regarding design-build-operate-main (DBOM), the new contracting formula
between the owner and the contractor. Studies within the area of DBOM, shows that there
are some potential regarding this kind of contracting but the railway sector is yet to be more
efficient regarding administration. Furthermore, studies shows that DBOM might be a
possible contract type within some technological areas of the railway sector and some
minor projects as well. The core subject of this thesis is to evaluate the forces behind
implementation of a possible contracting type like DBOM within the railway sector. The
outcome of this studies and conclusion drawn by the author shows that implementation of
the DBOM contracting type, as mentioned before, is yet to be implemented in minor fields
within the railway sector.
Regarding finance and infrastructure developments, the literature studies made within the
area of financing of infrastructure developments, delivers the theory of three kinds of
financing models within the infrastructure: government subsidy, government granted loan
and Public-Private-Partnership. Furthermore, some forces within the swedish government
solemnly issues that Public-Private-Partnership venture is equal DBOM contracting.
Studies regarding procurement shows that there various types of problems regarding the
process of procurement within the swedish railway administration and the infrastructure
area as well, could be shortened and more effective. The analyze regarding procurement
within the swedish railway administration, conducts certain amount of conclusion and
foremost that new kind of procurement method should be implemented within the swedish
railway administration, as of E-procurement or equal.
This thesis also contains a case study, Mälarbanan. The reason why a case study has been
conducted, is to evaluate whether if DBOM contracting type should be implemented within
Mälarbanan, a railway line between Tomteboda and Kallhäll. The analyze intermediates
possible threats regarding DBOM contracting type. Foremost, the DBOM contracting type
should not be implemented whereas there are some tunnels involved in the contract thus the
outcome (product) might differ from the request proposal and the specification given by the
owner, the swedish railway administration i.e. Secondly, the DBOM contracting form
should not be implemented regarding a railway line like Mälarbanan, the length of line
should be taken to consideration. Although there are some major/minor issues regarding
DBOM contracting type, the study recommends the swedish railway administration that
minor contracts should be the primary choice of the case of Mälarbanan.
The conclusion made by the author is regarding the swedish railway administration. The
analyze shows that and the conclusion conducted by the author relates to effectiveness and
the new kind of structure. Recent administration structures lacks efficiency regarding
implementation of new contracting types and as a result of lack of effectiveness have led to
consequences regarding lack of bids and lack of competition between entrepreneurs, but
foremost lack of innovation within the railway sector. Keywords: DBOM, procurement, effectiveness, finance.}},
  author       = {{Siddique, Samuel}},
  language     = {{swe}},
  note         = {{Student Paper}},
  title        = {{Funktionsentreprenader inom Järnväg - möjligheter och hinder}},
  year         = {{2009}},
}