Enablers and barriers to project planning and scheduling based on construction projects in Oman

Al Nasseri, Hammad LU and Aulin, Radhlinah LU orcid (2016) In Journal of Construction in Developing Countries 21.
Abstract
While the concepts of planning and scheduling seem to be adequately discussed in the project management literature, relatively few examples of factors specifically affecting the performance of planning and scheduling are to be found. The study reported in this paper investigated a set of factors identified as enablers and barriers to successful project planning and scheduling of construction projects in Oman. The study adopted a questionnaire-based survey to measure the impact of each factor. The data were analysed using the relative impact (or importance) index (RII). On the basis of RII rankings, the results revealed that the identified enablers and barriers were all considered significant. This could imply that all of the factors should... (More)
While the concepts of planning and scheduling seem to be adequately discussed in the project management literature, relatively few examples of factors specifically affecting the performance of planning and scheduling are to be found. The study reported in this paper investigated a set of factors identified as enablers and barriers to successful project planning and scheduling of construction projects in Oman. The study adopted a questionnaire-based survey to measure the impact of each factor. The data were analysed using the relative impact (or importance) index (RII). On the basis of RII rankings, the results revealed that the identified enablers and barriers were all considered significant. This could imply that all of the factors should be considered equally from the perspective of project planning and scheduling, including schedule control. In addition, the results suggest that project managers should pay attention to the more significant barriers to mitigate their potential impacts on planning and scheduling. Recommendations for mitigating those barriers are presented. The study provides useful insights into the impact of various factors on the planning and scheduling performance of construction projects in Oman and how improvement might be achieved. (Less)
Please use this url to cite or link to this publication:
author
and
organization
publishing date
type
Contribution to journal
publication status
published
subject
keywords
Oman., relative impact index, scheduling enablers, project planning, scheduling barriers
in
Journal of Construction in Developing Countries
volume
21
publisher
Universiti Sains Malaysia
external identifiers
  • scopus:85027283977
ISSN
1823-6499
DOI
10.21315/jcdc2016.21.2.1
language
English
LU publication?
yes
id
af0d4ed7-0c60-4f2d-b922-e6194fc70c13 (old id 7792434)
date added to LUP
2016-04-04 12:54:40
date last changed
2024-01-14 03:53:22
@article{af0d4ed7-0c60-4f2d-b922-e6194fc70c13,
  abstract     = {{While the concepts of planning and scheduling seem to be adequately discussed in the project management literature, relatively few examples of factors specifically affecting the performance of planning and scheduling are to be found. The study reported in this paper investigated a set of factors identified as enablers and barriers to successful project planning and scheduling of construction projects in Oman. The study adopted a questionnaire-based survey to measure the impact of each factor. The data were analysed using the relative impact (or importance) index (RII). On the basis of RII rankings, the results revealed that the identified enablers and barriers were all considered significant. This could imply that all of the factors should be considered equally from the perspective of project planning and scheduling, including schedule control. In addition, the results suggest that project managers should pay attention to the more significant barriers to mitigate their potential impacts on planning and scheduling. Recommendations for mitigating those barriers are presented. The study provides useful insights into the impact of various factors on the planning and scheduling performance of construction projects in Oman and how improvement might be achieved.}},
  author       = {{Al Nasseri, Hammad and Aulin, Radhlinah}},
  issn         = {{1823-6499}},
  keywords     = {{Oman.; relative impact index; scheduling enablers; project planning; scheduling barriers}},
  language     = {{eng}},
  month        = {{12}},
  publisher    = {{Universiti Sains Malaysia}},
  series       = {{Journal of Construction in Developing Countries}},
  title        = {{Enablers and barriers to project planning and scheduling based on construction projects in Oman}},
  url          = {{http://dx.doi.org/10.21315/jcdc2016.21.2.1}},
  doi          = {{10.21315/jcdc2016.21.2.1}},
  volume       = {{21}},
  year         = {{2016}},
}